New Wapley bridge may open any day

It’s possible that the new Sergeant’s Farm Bridge, which links Shire Way to Wapley Common, may open as soon as tomorrow (Sat 25 April).

If all goes to plan tomorrow, we understand that Murphys have Network Rail’s permission to remove the temporary bridge overnight Saturday/Sunday. Fingers crossed…

They have been installing the new boundary fence for the Network Rail compound. At least in the short term the path from the bridge will emerge at the zebra crossing, then people will be able to walk along the short length of tarmac on the edge of Shire Way and then follow the path back into the ashtrack.

It is hoped to organise a modest celebration event in the near future, possibly involving a local school. We’ll keep you posted.

Wapley workday deals with water, planting and rubbish

The Wapley Bushes Local Nature Reserve work morning on 14 March attracted 26 Wapley Bushes Conservation Group volunteers and friends, including family groups and a community work party from the Church of Jesus Christ of Latter-Day Saints.

We tackled a wide range of tasks. One party planted trees to form a barrier at the edge of the picnic area, while others cleaned up around the main paths and public areas, gathering around 15 bags of litter (plus a carpet from a roadside ditch)

Eager volunteers get a safety talk before all the planting and clearing
The third and heaviest job of the day was probably clearing silt from the water channel out of the top pond to stop it overflowing. A vital part of managing the Nature Reserve is controlling the flow of the water to conserve the various habitats. It was interesting to find a quantity of frogspawn in one part of the the top pond, something that had not been seen there before but which accounts for the frogs that are seen in the meadows.
“I think the water’s going down” – Paul Hulbert checks the depth

This video gives some idea of the amount of silt in the stream
We’re glad to report that the mud from railway works we mentioned recently has been partly cleared up, and arrangements have been made to reinstate the area concerned. The contractors now expect to be off site by the end of April.
P.S. If anyone still has two litter-picking tools from Saturday, please ring Paul on 07771 562505 to arrange to return them.

Mud, mud, glorious mud

Network Rail’s contractors have caused more damage to the grass than we anticipated, but we’re on the case.

As you can see, the big tracked vehicle and the tractor and trailer have been taken further into the mouth of the Lower Meadow than we had anticipated, and the whole entranceway is just mud.

There are also tracks on the near corner of the Common and to the side of the roadway in between.

The big tracked vehicle will be removed from the Common side of the bridge on Saturday night, crossing the railway track to get back to the compound. The tractor and trailer will finish their work on Monday. On Tuesday there should be a pavement sweeper on site to clean the mud off the tarmac roadway.

We are meeting the site manager on Monday morning to discuss the RADAR gate and ground reinstatement. The site manager appreciates that we’re not best pleased, while we do understand the practical difficulties of manoeuvring such large vehicles in such tight quarters.

On a related local note, we have also met South Glos this morning about the boggy patches on the “Ashtrack” footpath from Wapley Bridge towards Goldcrest Park. They have measured it up and agreed the necessary works, and they anticipate doing the work in June/July when Network Rail are well clear and the ground has dried up. Some parts of the path will just be topped up, the worst parts will be reconstructed and drainage will be put in at one or two points.

Fast progress on Wapley Bridge approaches

All the precast concrete units are now in place, and the big tracked vehicle should be crossing back over the line on Saturday night. Work is under way to fill in the sections with aggregate and then put the top surface on.

Obviously moving the tracked vehicle and the tractor backwards and forwards has created a reasonable amount of mud on the Wapley side. A street sweeping vehicle has been ordered for Tuesday to clear this up.

All systems go again on Wapley bridge works

The large tracked vehicle crossed the track overnight Saturday 28th February / Sunday 1st March and is now at work on the Common side of the line. It JUST fits on the approach ramp!

The first of the remaining precast concrete sections has been transported to the south side and lifted into place.

The sections are being moved by tractor and trailer via Besom Lane and Wapley Common.

Quiz Night Live! – Friday 13 March

This is your chance to have some fun and pick a team of Eggheads and bring them along to our general knowledge quiz in aid of Avon Wildlife Trust. You are most welcome make up a team name and bring your own snacks and beverages. We will also be serving tea and coffee for you in the break. Quiz teams are usually made up of four players at a cost of £2.50 per individual team member. Please contact Malcolm on 01454 310328 to book your team’s place. Venue: The Old Grammar School, High Street, Chipping Sodbury, 7.30pm.

Wapley Bridge – latest update

Residents will be aware that work on the bridge has slowed down dramatically over the the last few weeks. This was due to problems with the finish on some of the precast concrete units, but these have now been solved.

Another difficulty has been how to get the large tracked vehicle (the orange one in the photo) across to the other side of the line, because of the traffic restrictions on Besom Lane.

It is now planned to take the big vehicle across the railway track at night, possibly this coming weekend.

Work should then proceed quickly. The concrete sections will still be brought round to the other side on a trailer pulled by a large tractor, via Wapley Common as previously planned.

STOP PRESS: The big vehicle is due to cross the line on Saturday night (28 Feb). The concrete sections will be taken round next week, and most of the Beson Lane parking area will be coned off for the week so that they can get the big tractor and trailer in and out.